The hospital which is performed by Ekinciler - Dağ Construction Business Partnership has 400-bed capacity. The project, which is put on the tender on the date 15.11.2006 and then contracted on the date 22.12.2006, is constructed on a land of 102,208 m2 and the total construction area of the project is 77,200 m2.
The project will be completed in 1100 days.
|